January 27, 2016
RESULTS OF DEVELOPMENT OF THE ENERGY SECTOR OF UZBEKISTAN IN 2015
From the perspective of implementation of major priorities of development of economy joint-stock company \"Uzbekenergo\" takes necessary measures to ensure the sustainability of energy companies, a stable supply to consumers of electric and thermal energy.

Thus, in 2015, power plants of JSC \"Uzbekenergo\" produced about 55.5 billion kilowatt / hours of electricity at a growth rate of 104.2% and released 8.2 million Gcal of thermal energy.

During the year, it carried out the implementation of 26 major investment projects and completed the construction of eight power stations. In particular, last year completed modernization of hydraulic unit number 3 on Charvak HPP with replacement of the impeller. The company completed construction works for the main sites and initiated commissioning of the project \"Construction of a combined-cycle plant on Tashkent thermal power plant of 370 MW.\" During the implementation of measures to modernize and upgrade electrical grids provide input 0,4-6-10-35 kV transmission lines with total length of 912.3 kilometers, the order of 660 sets of transformer substations have been set. In order to diversify energy balance 15 projects has been implemented to increase use of alternative energy sources, including 12 projects for implementation of solar hot water systems.

According to JSC \"Uzbekenergo\"